1370 Wilbur Avenue — Garage Rebuild

10 · Construction Planning

Status: Preliminary feasibility studies exist

The construction sequence for this project is unusual: a steel frame must be erected around an existing garage while preserving the stucco walls and slab. This requires careful temporary works and access planning.

Key construction phases

  1. Demolition: Strip existing roof (shingles, felt, sheathing, rafters) while protecting the slab with plywood overlay. Asbestos test required for pre-1990 materials.
  2. Foundation excavation: Machine-auger 9 pier holes (24″ × 36″) around the existing garage. Hand-dig near slab edges.
  3. Foundation construction: Sonotube forms, rebar cages, concrete pour, anchor bolt setting. Special inspection required.
  4. Steel erection: Boom truck + ironworker crew (est. 3–4 days). Field-bolted connections at ~56 joints, field welding (~20 hours).
  5. Roof framing and weatherproofing: Secondary purlins, metal deck, underlayment, standing-seam roof. This must be weathertight before interior work begins.
  6. Wall assembly and interior: Framing, insulation, vapor barrier, drywall, interior metal panels.
  7. MEP rough-in: Electrical, lighting, detectors.
  8. Finishes: Painting, loft deck, flooring, stair/ladder, doors, windows.
  9. Solar: PV panel mounting and electrical tie-in (may be phased separately).

Temporary works

Inspection milestones