1370 Wilbur Avenue — Garage Rebuild

04 · Geotechnical & Foundations

Status: Planned

A geotechnical investigation has not yet been performed. The need for one depends on:

Foundation concept

The current design assumes 9 pier foundations, one for each steel column. Each pier is approximately:

Total concrete: ~3.1 cubic yards | Total excavation: ~5 cubic yards

What a geotechnical report would establish

The structural engineer will require geotechnical design parameters before finalizing foundation sizes and reinforcement. Whether a full geotechnical report is required or a simpler investigation suffices will be determined through coordination with the City and the structural engineer.